How_do_I_print_the_Project_Accounting_Update_report_2024.05_

How do I print the Project Accounting Update report? (2024.05)

You can use this report to

  • review the Project Accounting transactions that will be updated to the Project Accounting application. This option will not create new transactions. 

  • confirm the Project Accounts that have been updated to the Project Accounting application. This option will create new transactions. 

 

This view was updated with a new look and feel in the 2024.05 release. 

 

1. Open Connect Accounts Payable > Organization > Update Project Accounting. 

2. Select the period to update transactions to. 

3. Select Report Only from the Print menu. 

Print menu 

 

4. Click GO (CTRL+G). 

The transactions that will be posted to Project Accounting print on the Update report. None of the transactions are posted to Project Accounting.

 

1. Open Connect Accounts Payable > Organization > Update Project Accounting. 

2. Select the period to update transactions to. 

3. Select Report from the Print menu. 

Print menu 

 

4. Click GO (CTRL+G). 

 

 

 

 