Instructions for:
Setting up SUTA Wage List (CO) by SUTA type
Setting up SUTA Wage List (CO) - Amended
Running SUTA Wage List (CO)
Running SUTA Wage List (CO) - Amended
1. Go to Payroll > State Reports > SUTA Wage List.
2. If the data has multiple states, select Colorado from the list.
3. On the Select Report Type dialog, select the SUTA Wage List (CO)
4. On the Report Options tab:
Verify the reports dates are the correct reporting period.
Select the Include option you would like to run.
Report- only prints the Caselle report
Report and state file- Prints the Caselle Report and creates the electronic state file
State file- creates the electronic state file
Verify the File transmission is set to SUTA.
5. On the State Reporting tab:
The Options and Setup subtabs are already set with the needed information.
On the Fields subtab, select the SUTA pay code using the select button at the top left of the field.
6. On the State file tab, go to the Export Settings subtab and set the file name/path.
The file path can be typed in, pasted in, or browsed to.
The expected file name is COSUTAYYYYQ.csv
7. If you would like the report to prompt for conversion when the report is opened, click the options button in the toolbar, check the box, and click OK.
8. Select save in the toolbar and name the report.
9. To save this new report as the default report:
Select the options button from the toolbar
On the Default report drop down, select the newly saved report.
Click OK.
Select to the desired save option.
1. Go to Payroll > State Reports > SUTA Wage List.
2. If the data has multiple states, select Colorado from the list.
3. On the Select Report Type dialog, select the SUTA Wage List (CO)
4. On the Report Options tab:
Verify the reports dates are the correct reporting period.
Select the Include option you would like to run.
Report- only prints the Caselle report
Report and state file- Prints the Caselle Report and creates the electronic state file
State file- creates the electronic state file
Verify the File transmission is set to Adjustment.
5. On the State Reporting tab:
On the Options tab, select the needed Adjustment reason code
The default is reason one. This field will need to be verified and changed as needed when running the report.
The setup tab does not need anything to be setup on it.
On the Fields subtab, select the SUTA pay code using the select button at the top left of the field.
6. On the State file tab, go to the Export Settings subtab and set the file name/path.
The file path can be typed in, pasted in, or browsed to.
The expected file name is COSUTAYYYYQ.csv
7. Select save in the toolbar and name the report.
1. Go to Payroll > State Reports > SUTA Wage List
2. If the data has multiple states, select Colorado from the list.
3. On the Select Report Type dialog, select SUTA Wage List (CO)
4. Select the needed Report Definition
5. Verify the report dates are the needed reporting period
6. Two options to proceed, if the data has not already been converted.
Select Preview. (Option 1)
If the dates have changed since the data was converted, a dialog will appear confirming which dates and data needs to be seen.
If Yes is selected, review the information on the Review tab and then click Preview again.
If No is selected, the report and electronic file will create using the dates from the review tab.
Go to the Review tab and click refresh. (Option 2)
Review the information on the review tab and then click Preview to create the report and file.
1. Go to Payroll > State Reports > SUTA Wage List
2. If the data has multiple states, select Colorado from the list.
3. On the Select Report Type dialog, select SUTA Wage List (CO)
4. Select the needed Report Definition.
5. Verify the report dates are the needed reporting period
6. Go to the State Reporting tab, on the options tab select the adjustment reason code that explains why the adjustment file is needed.
7. Two options to proceed, if the data has not already been converted.
Select Preview. (Option 1)
If the dates have changed since the data was converted, a dialog will appear confirming which dates and data needs to be seen.
If Yes is selected, review the information on the Review tab and then click Preview again.
If No is selected, the report and electronic file will create using the dates from the review tab.
Go to the Review tab and click refresh. (Option 2)
Review the information on the review tab and then click Preview to create the report and file.